SBB ENERGY S.A. signed a contract for the modernization of three BP-1150 boilers in Opole Power Plant

We are pleased to announce that on 12th June 2018 a contract between PGE GiEK.SA El. Opole and SBB Energy S.A. for the modernization of three BP-1150 boilers was signed. The aim of modernization is to reduce the emission of nitrogen oxides NOx below 150 mg / Nm3.


2018-06-13

Kamień węgielny

We are pleased to announce that on March, 2nd 2018 the groundbreaking ceremony of a proecological investment led by SBB ENERGY S.A. at Bydgoszcz CHP Complex took place. The object of the task is to build by SBB ENERGY S.A. in a turnkey basis a complete, modern installation of catalytic nitrogen oxides reduction of flue gases for boilers type OP-230 No. 3 and 4 (hard coal-fired, with a capacity of 230 Mg/h of steam each) at Bydgoszcz CHP Complex covering its design, manufacture, delivery, assembly, start-up, optimization and commissioning. The investment is aimed at a fourfold NOx reduction and thus will meet stringent EU environmental requirements that will be applied from 2021. We wish the whole team coordinating the project its successful and timely completion.


2018-03-07

Charity campaign for the Home of the Single Mother - Monar Markot Zopowy.

We are pleased to announce that  SBB ENERGY S.A. once again joined the charity campaign for the Home of the Single Mother - Monar Markot Zopowy.

We sincerely hope that collected gifts will help people supported by the association to get away from everyday struggle and to forget for a while about problems they have to face.

Special thanks to the whole SBB Team for your generosity and commitment to this action!

Remember, good returns!


2018-02-20

LATEST PROJECTS

  • Principal:
    EDF Polska S.A. Elektrociepłownia Gdynia
    Customer:
    EDF Polska S.A. CHP Gdynia
    Scope of work:

    Execution of installation works in the construction of primary and SNCR methods plant on two boilers BC-50 in CHP Plant in Gdynia as General Constructor.

  • Principal:
    Veolia Energia Poznań - Zespół Elektrociepłowni S.A.
    Customer:
    CHP Poznań
    Scope of work:

    Execution of installation works in the construction of DeNOx by SNCR method on boilers 1K2, 2K, 3K in CHP Plant Karolin in Poznań.

  • Principal:
    ELEMONT SP. Z O.O
    Customer:
    PGE GiEK S.A. Oddział Elektrownia Opole
    Scope of work:

    Installation and lightening in buildings 5UHA and 6UHA in the construction of power units in Opole Power Plant..

  • Principal:
    KRALOPOLSKA RIA - Elektrownia Chvaletice w Czechach
    Customer:
    CHP Chvaletice, Czech Republic
    Scope of work:

    DeNOx installation for two boilres K3 and K4.

  • Principal:
    Veolia Energia Poznań - Zespół Elektrociepłowni
    Customer:
    CHP Poznań
    Scope of work:

    DeNOx system installation for all three units.

  • Principal:
    EDF Polska S.A. Elektrociepłownia Gdynia
    Customer:
    CHP Gdynia
    Scope of work:

    Adaptation of boilres to meet the requirements for NOx emmisions using primary and secondary SNCR methods.

  • Principal:
    Elektrociepłowania Będzin Sp. z o.o.
    Customer:
    CHP Będzin
    Scope of work:

    Execution of installation works in the construction of DeSOx and DeNOx in CHP Plant in Będzin for boilres no. 7, no.6, no.5 as General Contractor.

  • Principal:
    Andritz Energy&Environment GmbH
    Customer:
    Mjölby / Sweden
    Scope of work:

    Commissioning works on biomas unit in Mjölby, Sweden

  • Principal:
    E.ON ENERGY
    Customer:
    Marl / Germany
    Scope of work:

    Start ups in Chemical Industrial Plant

  • Principal:
    ALSTOM s.r.o.
    Customer:
    Ledvice/Czech Republic
    Scope of work:

    Commissioning works on unit 660 MW in Ledvice,  Czech Republic

REFERENCES: