Retrofit projects in power industry and other sectors

Principal
Customer
Scope of work Completion date
KRALOPOLSKA RIA - Chvaletice Power Plant, Czech Republic
CHP Chvaletice, Czech Republic

DeNOx installation for two boilres B2.

2016-03-14 to 2017-02-03
PGE GiEK S.A. Oddział Elektrownia Opole
Opole Power Plant

DeNOx system installation in Opole Power Plant. Boilers at power units 1,2 and 4. BP- 1150 boilers fired with coal + biomass.

2013-02-01 to 2016-07-01
Zespół Elektrowni Pątnów Adamów Konin S.A.
Pątnów Power Plant

Modernization of K1 and K2 boilers in Pątnów Power Plant. OP-650 lignite fired boilers.

2013-07-01 to 2015-12-01
PGE GiEK S.A. Oddział Elektrownia Turów
Turów Power Plant

Installation of the SNCR in Turów Power Plant. Boilers of power units 4,5,6. OFZ lignite fired boilers.

2014-02-01 to 2015-11-01
Zespół Elektrociepłowni Wrocławskich KOGENERACJA S.A.
CHP Wrocław

Installation of SNCR system at BC1 boiler in Wrocław CHP Plant. OP-230 boiler fired with coal + biomass.

2012-03-01 to 2014-02-01
PGE GiEK S.A. Oddział Elektrownia Turów
Turów Power Plant

SNCR system installation in Turów Power Plant. Boilers of power units 1,2,3. OFZ - 670 lignite fired boilers.

2012-06-01 to 2013-12-01
Principal
Customer
Scope of work Completion date
KRALOPOLSKA RIA - Elektrownia Chvaletice w Czechach
CHP Chvaletice, Czech Republic

DeNOx installation for two boilres K3 and K4.

form 2015-11-01
Veolia Energia Poznań - Zespół Elektrociepłowni
CHP Poznań

DeNOx system installation for all three units.

form 2015-11-01
EDF Polska S.A. Elektrociepłownia Gdynia
CHP Gdynia

Adaptation of boilres to meet the requirements for NOx emmisions using primary and secondary SNCR methods.

form 2015-11-01
Elektyrociepłowania Będzin Sp. z o.o.
CHP Będzin

Construction of DeNOx and DeSOx systems for two OP-140 boilers no. 6 and 7 and one WP-70 boiler no. 5.

form 2014-09-01

REFERENCES: